Application for Construction and first work samples

The implementation of the construction continues. As mentioned in the last blog post, there is a lot to organize and think about. I signed the building application today and it goes directly to the office by messenger. An architect’s office neatly drew the site plan and the floor plan of the column and prepared all the necessary papers for the application.

The steelworker is already active and starts with the conception. He has already lasered a profile in 5 mm Corten steel. The result meets my/our expectations. Looks great! I met with the lighting designer yesterday and we simulated the effect of the lighting on the old 5 metre corrugated cardboard model. The result was not yet satisfactory and so we continue to work on it.

The city of Hamburg has yet to accept the Column as a gift. It was discussed in online conversations. The structural engineer’s documents are still missing, who is waiting for the core drilling to be evaluated. Keep your fingers crossed that the authorities will follow suit and that everything will go quickly and smoothly so that it can be completed this year.

P.S.: Due to the increased raw material prices, additional construction costs are to be expected. So not all areas for the production of the Column are fully financed yet. In this respect, we have decided to also name sponsors on the column. As originally planned, the names of supporters and some companies will now be mentioned. We continue to rely on private investments (more on this under “Team”).

Share:

Leave a Reply

Your email address will not be published. Required fields are marked *

Similar Posts

Realisation
Björn

We invite you to the inauguration

The column is now freely accessible and we cordially invite you to the inauguration on August, 2023 at 7 p.m., Schweriner Straße, 22143 Hamburg After

Realisation
Björn

Column of Connectedness has been erected

Yesterday afternoon, on June 27th, 2023 at 4:30 p.m. sharp, the Column took its final place. It was an enormous effort and a nail-biter until

Realisation
Björn

The foundation is ready

The concrete foundation on Schweriner Strasse has been hardening since mid-May 2023. After excavating the ground, dredging, reinforcement, formwork, electrostatic grounding and laying rainwater and

Realisation
Björn

The team works in the background

You haven’t heard from us for a long time and it seems to have become quiet about the Column. But the fact is that the

Realisation
Björn

The Building Permit

Dear friends, the authorities have approved the construction of the column! We are still stunned by the great news and super happy! Four years have